fbpx

Start building better today.

Are you ready to work with some of the best in the business? Contact us today to start your next commercial concrete project.

502.222.0303

4608 Old Lagrange Rd
Buckner, KY 40010

Close
Close

Start building better today.

Are you ready to work with some of the best in the business? Contact us today to start your next commercial concrete project.

502.222.0303

University of Kentucky

Shivley Track & Field Concrete

Case Studies

2,000 LF

Retaining Walls


16' Tall

walls with brick reveals


2,500 CY

Concrete


University of Kentucky – Shively Track & Field Project

E&W clears hurdles to complete track retaining walls

East & Westbrook was the selected contractor for the structural concrete for the new university of Kentucky Shivley Track and Field complex.  This work included over 2,000 lineal feet of cast in place concrete walls and retaining structures exceeding heights of 16’. The work was completed in one of the rainiest summers in recent history for the Lexington, KY area. This required the construction schedule to be compressed in order to complete the facility before the opening spring track meet. A major effort went into coordination of other trades working onsite, including the specialty track surface installation contractor that was scheduled more than 12 months in advance.

While hurdles such as poor weather can be encountered on many construction projects, when the completion date is fixed because of scheduled events, it requires strong project management and quality leadership and performance in the field to cross the finish line.

East & Westbrook Vice-President Chad Snellen's Headshot

Meet the Project Manager, Chad Snellen, PE

Vice-President • 21 years' experience

Chad has a Bachelor’s Degree in Civil and Environmental Engineering and a Master’s Degree Facility Engineering (Emphasis in Structural and Geotechnical Engineering). Chad has over 20 years of experience in Engineering and Construction as a field technician, engineering consultant and project manager for commercial, institutional and industrial construction projects.

Want to work with Chad?

Shot of Walls Slowly Being Erected on the UK Construction Site

Some walls were close to ther structures

Foundations Being Prepped for Retaining Walls

Foundations are prepared for retaining walls

Forms Being Re-Set for the Next Wall Pour

As walls are poured, forms are re-set for the next pour

North American Stainless Steel Bar Turner Foundation In-Progress

Crews place reinforcement and set panels